Conditions:
In order to synchronize a generator to the grid, four conditions must be met:
- Phase Sequence
- Voltage Magnitude
- Frequency
- Phase angle
Synchronizing procedure
It must also be noted that load distribution can be adjusted by varying the fuel supply to the generator via its governor but for current sharing to be equal you would need to vary the excitation current which changes the power factor of the generator.
- Once the engine starts running properly, synchronization is carried out.
- In the Engine control room, Check the pressure gauges.
- On the generator control panel, check if all the ground lights are working properly with adequate brightness.
- Also check the synchronizing relays for open position. Bring the running or the lead generator to the desired optimum parameters: 480 volts and 60 hertz.
- Bring the generator that is to be synchronized(in-coming) to the desired parameters. Now turn on the synchronizing relay and keep a close look at the needle.
- The needle in the synchroscope will move at a varying speed initially. Adjust the speed of the generator by obtaining a steady slow motion of the needle in the clock wise direction.
- Once the needle is moving at a steady speed, depress the breaker close button when the needle has traveled three-fourth of its way. Energize the breakers when the needle reaches a position similar to the 11' o clock position of a clock.
- After doing this, check the parameters of the on-coming generator. They should be same as those of the leading generator. i.e 480 Volts and 60 hertz
- After the main job of synchronizing, the following steps are to be carried out.
- Change the governor control to the off-going generator.
- Now the load shown in the gauges by this generator should be removed off the system as soon as possible before it starts acting as load(reverse power). This can be done by quickly pulling the trip breaker as soon as the generator goes off-line.
- Once the generator is offline, stop the engine using a toggle switch.
- After turning off the engine, turn on the engine block heater.
- At the end, take a proper look at the control panel gauges for adequate pressure and even distribution of load.
It must also be noted that load distribution can be adjusted by varying the fuel supply to the generator via its governor but for current sharing to be equal you would need to vary the excitation current which changes the power factor of the generator.
----------------------------------------------------------------------------------------
See the best Pure IT PK is a leading solution Water filtration Plants in pakistan and corporate sector at large,
ReplyDeletefor all problems related reverse osmosis plant ,waste water treatment
, water softner plants and Mineral Water Plant .
We fulfilling customer satisfaction with wide range of quality products Water and milk Chiling System
and water filter treatment field “Pure It Pk” is a leading manufacturer of completely integrated
RO & UF plants with engineering, installation & commissioning of more than 300 units in Pakistan.
if you are interested in Best football picture PLease Visit this website International soccer
ReplyDeletereverse osmosis plant
Home Tutor in Lahore
best marquee services in lahore
M4 Smart Bracelet
Fabrication Advanced Engineering (Pvt) Ltd. was established in 1997 in the surburbs of Lahore as Adjustable Racks Company. best rack in lahore Our services include all types of storage racks for organizations big and small.
Wonderful blog post. This is absolute magic from you! I have never seen a more wonderful post than this one. You've really made my day today with this. I hope you keep this up!
ReplyDeleteayesha name meaning in Urdu 2020
Design automation provides complete configuration and automation solutions using DriveWorksWe offer design and automation solutions matched with flexibility and ease of use, Our expertise enables our clients to generate customized 3D CAD models, Automation software and 2D drawings. DriveWorks live design Automation & Sales Configurator DriveWorks software is used by companies large and small. It is ideal for engineer that needs Design Automation to automate your SOLIDWORKS models. Also, for companies wanting to provide Product Configurator. Our Company provides complete a. industrial designers nd automation solutions using DriveWorks.
ReplyDelete